Prove it is safe enough to dose people: GLP toxicology, first GMP batch, IND or CTA.
Open this in the interactive map →
What happens The work of this stage
Everything needed to justify dosing humans. Pivotal safety studies under GLP: repeat-dose toxicology in a rodent and a non-rodent (ICH M3(R2): at least as long as the planned clinical dosing and a minimum of two weeks, so 28-day studies are the common package for early trials; one pharmacologically relevant species is often accepted for biologics under ICH S6(R1)), safety pharmacology core battery, genotoxicity (small molecules), toxicokinetics. The first GMP batch of drug substance and drug product is made, formulated for first-in-human use, released and put on stability. Analytical methods are developed and qualified. Regulatory strategy is set at a pre-IND (US) or scientific advice (EU) meeting, then the IND or CTA is written.
Functions active 9 functions busy
Toxicology and pathologyDMPK and bioanalysisCMC: process or route development, formulationAnalytical developmentQuality (GLP QAU, first GMP release, QP in EU)Regulatory affairs (pre-IND, IND or CTA authoring)Clinical (protocol, Investigator Brochure)Clinical pharmacology (dose projection)Manufacturing or CDMO management
GxP that applies Regulations and validation
GLP for the pivotal nonclinical safety studies (21 CFR Part 58, OECD GLP). GMP begins with the first clinical batch: phase-appropriate GMP for investigational medicinal products (FDA guidance on cGMP for Phase 1 investigational drugs, 2008; in the EU, Delegated Regulation 2017/1569 and the Detailed Commission guideline on GMP for IMPs, which replaced Annex 13 for trials under the Clinical Trials Regulation). Computerised system validation now applies to systems holding GLP and GMP records.
Key deliverables 7 outputs
- IND (US, 21 CFR 312) or CTA (EU, submitted through CTIS under Regulation 536/2014)
- IMPD or CMC section: DS and DP manufacture, controls, preliminary specifications, initial stability
- Investigator Brochure (IB)
- Phase 1 protocol and informed consent
- GLP toxicology and safety pharmacology reports
- First GMP batch with certificate of analysis; reference standard
- Qualified analytical methods; stability protocol started
Gate decision at the end What has to be true to move on
IND clearance or CTA authorisation. FDA has 30 days to object; silence means the study may proceed. In the EU the CTA is assessed through CTIS by a reporting member state: about 60 days without questions, up to about 106 days when requests for information are raised (longer for ATMPs). Internally, the gate is often "FIH-ready" plus a budget release for Phase 1.